APPSC Assistant Executive Engineer ( Paper 3 ) 2012 MCQs - 5

Question 1 of 25

Find out cost per unit from following data : Fixed cost Rs. 20 × 105, variable cost = Rs. 30 × 105, unit generated per annum = 175 × 106 kWh
Rs. 1.00
28.57 Paise
5 Paise
2.85 Paise

Well Done!
Correct Answers : /
Correct Answer In Percentage :