Greatest demand of load during given period
( 2 ) Connected load
= Sum of all continuous rating of load
- If consumer has four equipment and its rating are 500 W, 1 kW, 60 W and 40 W, the connected load = 500 W + 1000 W + 60 W + 40 W = 1600 W
( 3 ) Average load
- The average load is given for specify time say daily, monthly or yearly.
- Average load ( daily )
- Average load ( Monthly )
- Average load ( Yearly )
( 4 ) Load factor
= Average demand / Maximum demand
= Average demand × time / Maximum demand × time
= No. of unit generated in given time / Maximum demand × time
( 5 ) Demand factor
=
Maximum demand / Connected load
( 6 ) Diversity factor
=
Sum of individual maximum demand / Maximum demand
( 7 ) Plant capacity factor
= Average demand / Plant capacity
= Actual energy produced / Maximum
energy have been produced
( 8 ) Plant capacity factor ( Yearly )
= Yearly kWh output / [ Plant capacity × ( 365 × 24 ) ]
( 9 ) Plant use factor
= Station output in kWh /
[ Plant capacity × Plant operation in hours ]
( 10 ) Reserve capacity
= Plant
capacity – Maximum demand
If the maximum demand is
same, load factor is equal to plant capacity.
You may also like :
Important Formula of Annual
Depreciation Charges
Important Formula of Transistor
Biasing
Important Formula of Negative
Feedback Amplifier
Important Formula of Transistor
Tuned Amplifier
Important Formula of Symmetrical
Fault Analysis
No comments:
Post a Comment